Vacate
CP-2025-TN246-0014-ADOSH · Arizona Division of Occupational Safety and Health · 2026-01-16
IN THE OFFICE OF ADMINISTRATIVE HEARINGS
DIVISION OF OCCUPATIONAL SAFETY AND HEALTH OF THE INDUSTRIAL COMMISSION OF ARIZONA, Complainant
v.
GARNEY COMPANIES, INC.
Respondent
No. CP-2025-TN246-0014-ADOSH
FINDINGS & ORDER APPROVING SETTLEMENT AGREEMENT
On April 10, 2025, the Division of Occupational Safety and Health of the Industrial Commission of Arizona (“ADOSH” or “Division”) inspected a worksite of Garney Companies Inc. (“Respondent” or “Garney Companies Inc.”) located at SW Corner of S. Greenfield Rd. and E. Main Street, Mesa, AZ 85205, Inspection No. CP-2025-TN246-0014. This inspection resulted in the Complainant issued a Citation and Notification of Penalty to the Respondent on September 4, 2025.
WHEREAS, Respondent timely filed a Notice of Contest with respect to the above-mentioned citation, and the Division and Respondent now desire to settle this matter without the necessity of a formal hearing, both parties agree that it is in their respective best interests to settle this matter without going through the procedures, time and expense associated with litigation and a formal hearing.
FINDINGS AND CONCLUSIONS
NOW, THEREFORE, the parties agree to settle this matter as follows:
On December 31, 2025, the parties filed a Settlement Agreement resolving all issues and disputes involved in this matter. The Settlement Agreement appears to be consistent with the provisions and objectives of the Arizona Occupational Safety and Health Act. Accordingly, pursuant to A.A.C. R20-5-827 of the Occupational Safety and Health Rules of Procedure Before the Industrial Commission of Arizona, the Settlement Agreement is incorporated by this reference, adopted, and made a part of this order.
The Settlement Agreement is in furtherance of the purpose of the Arizona Occupational Safety and Health Act of 1972 and represents a full and final determination of this matter.
ORDER
IT IS HEREBY ORDERED that:
Citation 1 Item 1 and the associated penalty will be deleted.
IT IS FURTHER ORDERED that Respondent:
1. Contact ADOSH consultation within 30 days of the effective date of the Settlement Agreement to schedule a Pre-Safety and Health Achievement Recognition Program (“SHARP”) evaluation visit with ADOSH Consultation Services in the 6-month period following the effective date of the Settlement Agreement.
2. Join the ADOSH Trenching Alliance and provide a presentation to the Trenching Alliance as detailed in the Settlement Agreement incorporated by reference.
IT IS FURTHER ORDERED that each party is to bear its own attorney’s fees and costs.
NOTICE
Any party dissatisfied with this Decision may request review by the Review Board, filing a written request with the Administrative Law Judge Division of the Industrial Commission within fifteen (15) days after service of this Decision as provided by Arizona Revised Statutes, §§ 23-421(C) and 23-423(A) and (B). If no such request is made within the time provided, this Decision becomes final.
By: Tammy L. Eigenheer
The Honorable Tammy L. Eigenheer,
Administrative Law Judge
DATED IN PHOENIX, ARIZONA, THIS 16th day of January, 2026.
BEFORE THE OFFICE OF ADMINISTRATIVE HEARINGS
CERTIFICATE OF SERVICE
The attached FINDINGS & ORDER APPROVING SETTLEMENT AGREEMENT was placed in, and is now a part of, the Office of Administrative Hearings file and was served on the parties named below via mail/email/facsimile on 16th day of January, 2026.:
Brian Hudson
Division of Occupational Safety & Health
800 West Washington Street
Phoenix, AZ 86007
[email redacted]
ADOSH Director
Sophia Cox, Esq.
Legal Division
Industrial Commission of Arizona
800 West Washington Street, Suite 303
Phoenix, AZ 85007
[email redacted]
[email redacted]
Attorney for ADOSH
Garney Companies, Inc.
Patrick Miller, Esq.
Dan Smolik, Owner
370 East Crown Point Road
Winter Garden, FL 34787
[email redacted]
[email redacted]
Respondent
By: OAH Staff