Minute Entry Continuance
2026A-02550-NPC-ROC · Registrar of Contractors · 2026-06-04
IN THE OFFICE OF ADMINISTRATIVE HEARINGS
Hector Mario Ramirez,
DBA: G B U Drywall,
COMPLAINANT
v.
3R Construction Group LLC
License No. ROC 341791,
RESPONDENT
No. 2026A-02550-NPC-ROC
ORDER GRANTING CONTINUANCE
At the time set for hearing in the above-entitled matter, the parties agreed to continue working toward resolution. To provide additional time, the hearing in the above-entitled matter is continued and set for a Status Update on August 28, 2026. On or before this date, the parties are advised to do one of the following:
(1) Inform the tribunal that the matter has been satisfactorily resolved by submitting a Motion to Vacate the hearing;
(2) Inform the tribunal that the parties need additional time to resolve the matter by submitting a Motion to Continue and reset for Status by 30-days, 45-days, or 60-days; or
(3) Inform the tribunal that the parties are unable to resolve their dispute and request that the matter be set for hearing.
Done this day, June 4, 2026.
/s/ Fahd Nazir
Administrative Law Judge
Transmitted by either mail, e-mail, or facsimile to:
Tom Cole, Director
Registrar of Contractors
[email redacted]
3R Construction Group LLC
[email redacted]
Hector Mario Ramirez
DBA: G B U Drywall
[email redacted]
By: OAH Staff