ALJDEC - Licensing

2025A-02113-CHC-ROC · Registrar of Contractors · 2025-09-23

IN THE OFFICE OF ADMINISTRATIVE HEARINGS

Wendy Bock

COMPLAINANT,

v.

Mariner LLC,

License No. ROC 340994,

RESPONDENT.

No. 2025A-02113-CHC-ROC

ADMINISTRATIVE LAW JUDGE DECISION

HEARING: September 4, 2025

APPEARANCES: Wendy Bock (hereinafter “Complainant”) appeared on behalf

of herself. Claudio E. Iannitelli, Esq. appeared on behalf of Mariner LLC (hereinafter “Respondent”).

ADMINISTRATIVE LAW JUDGE: Velva Moses-Thompson

_____________________________________________________________________

FINDINGS OF FACT

1. Complainant and Respondent entered into a contract, wherein Respondent agreed to construct a new wood frame residence for the amount of $494,000. Complainant paid Respondent at least $332,000 for the project. The scope of the contract included, but was not limited to, electrical, concrete, IT wiring and Equipment, and roofing.

2. Respondent did not provide Complainant with a written contract that advised Complainant of her right to file a complaint with the Arizona Registrar of Contractors (hereinafter “Registrar”) against Respondent for an alleged violation of Ariz. Rev. Stat. § 32-1154(A) within the time allowed by Ariz. Rev. Stat. § 32-1162(A).

3. On or about August 21, 2022, Respondent started work.

4. On or about May 31, 2024, Respondent stopped work.

5. On or about February 28, 2025, the Registrar received a complaint from Complainant alleging poor work and abandonment on the part of Respondent.

6. On or about April 10, 2025, Daniel Otero, an investigator for the Registrar, (hereinafter “Investigator Otero”), conducted a job-site inspection regarding the complaint.

7. On April 18, 2025, the Registrar issued a Directive to Respondent requiring that Respondent correct the following items by appropriate means, no later than 5:00 p.m. on May 6, 2025:

Complaint Item: 5 - Inside doors hung crooked, with large gaps and without knobs.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, the fire door and master bed room closet doors were out of square in their jambs, this was evident when the doors were close as well as slightly unlatched. Also the man door leading outside from the garage was not installed or sealed properly, along with the door for the upstairs apartment which was also not installed properly and lead to water intrusion. The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A) (3) - R4-9-108(A) Workmanship

Complaint Item: 6 - Cabinets installed crooked, uneven with multiple screws that cause damage.

Investigator’s Observation: Verified. At the time of the Inspection it was observed in the kitchen and laundry room. There were multiple cabinets that were poorly installed in many areas of the house. In the laundry room, the base cabinet was not installed at all but only halfway placed in its location. Trim and moldings were not installed but were on site. The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A) (3) - R4-9-108(A)

Workmanship

Complaint Item: 8 - Upper door installed incorrectly causing severe flooding of entire upstairs.

Investigator’s Observation: Verified. At the time of the Inspection it was observed the door on the upstairs apartment, there were no stairs built to get to the door for operation along side with the door being installed substandard. This allowed the wood sub floor take on water during storms that was damaged, also causing drywall damage below in the garage ceiling. The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A) (3) - R4-9-108(A) Workmanship

Complaint Item: 9 - Concrete around house is crumbling, cracking and pulling.

Investigator’s Observation: Verified. At the time of the Inspection it was observed on the newly poured sidewalk around the garage has cracking since it did not have control joints to serve their purpose and allow cracking in strategic areas. The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A) (3) - R4-9-108(A) Workmanship

Complaint Item: 10 - Did not complete any steps or decks but was paid to do

Investigator’s Observation: Verified. At the time of the Inspection it was observed there were no safe stairs with handrails built to access the upstairs apartment. At the time of the inspection a ladder is in place to conduct the inspection. The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A) (1)

Complaint Item: 11 - Did not complete any closets but was paid to do so. Investigator’s Observation: Verified. At the time of the Inspection it was observed the closets were not completed with shelves and rods. In the entryway of the house there is a "mudroom" area that was started but never completed along with the work that was done was not done in a professional workmanship like manner. The Respondent will need to correct this by the appropriate means. Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A) (3) - R4-9-108(A) Workmanship

Complaint Item: 12 - Did not remove all old concrete but was paid to do so. Investigator’s Observation: Verified. At the time of the Inspection it was observed in the areas where the old concrete was placed for the previous house prior to the fire. The Respondent will need to correct this by the appropriate means. Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A) (1)

Complaint Item: 15 - Cabinet pull holes drilled incorrectly and no pulls provided. Investigator’s Observation: Verified. At the time of the Inspection it was observed the holes were drilled for the cabinet pulls but there were no pulled installed or on site. The Respondent will need to correct this by the appropriate means. Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A) (1)

Complaint Item: 17 - Plumbing in master bath had to be relocated.

Investigator’s Observation: Verified. At the time of the Inspection it was observed &demonstrated, in the master bathroom under the right vanity. One of the drawers in the brawer bank between the vanities will not close due to the plumbing being placed in the wrong location, the drain will not allow the drawer to completely close. The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A) (3) - R4-9-108(A) Workmanship

Complaint Item: 18 - He did not complete interior trim or finish work but was paid to do so.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, as indicated in item 6 of the Written Directive there were cabinets, trim, toe kicks, finish accessories for the hood vent cover and moldings that were not installed. The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A) (1).

Complaint Item: 19 - Fireplace built in correctly and crooked and has to be redone.

Investigator’s Observation: Verified. At the time of the Inspection it was observed & demonstrated, the fireplace was not yet installed but the mantel over the fireplace location was not done in a workmanship like manner. The ends of the mantel were higher on both ends than the rest of the mantel. Respondent will need to correct this by the appropriate means. Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A) (3) - R4-9-108(A) Workmanship

Complaint Item: 22 - No plan for rain gutter drainage.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, gutters were not completed on the house since the stone veneer has not been completed. The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A) (1)

Complaint Item: 23 - Did not complete Plumbing or electrical to pool house and was requested to do so many times.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, there were wire as well as conduit out of the ground where the pool equipment was once located and was never reinstalled during the reconstruction of the project. The utilities that were exposed did not appear to be safe. The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A) (1)

Complaint Item: 24 - Painting / touch ups not done. Investigator’s Observation: Verified. At the time of the Inspection it was observed there was a substantial amount of paint touch-up that was not done or was not done in a professional like manner. The Respondent will need to correct this by the appropriate means. Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A) (3) - R4-9-108(A) Workmanship

Complaint Item: 25 - Great room fan not hung.

Investigator’s Observation: Verified. At the time of the Inspection it was observed the ceiling fan in the great room was sitting on the floor and had not been installed yet The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A) (1)

Complaint Item: 26 - Guest room fan broken.

Investigator’s Observation: Verified. At the time of the Inspection it was observed & demonstrated, when the fan was turned on it made a very loud clicking noise and had a wobble. The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A) (3) - R4-9-108(A) Workmanship

Complaint Item: 27 - Doors not painted.

Investigator’s Observation: Verified. At the time of the Inspection it was observed the master bedroom closet door was not painted on all six sides as required. There were also other doors throughout the house that were missing paint on the tops and bottoms. The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A)(3) - R4-9-108(A) Workmanship

Complaint Item: 28 - Exterior door jams not painted.

Investigator’s Observation: Verified. At the time of the Inspection it was observed on all of the exterior door jambs were not prepped, primed or painted, The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A)(3) - R4-9-108(A) Workmanship

Complaint Item: 29 - Construction trash not picked up.-No stone on house.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, there was a substantial amount of construction debris around the entire property as well as some in the neighbor’s property. Stone was also missing on the entire house where it was to be installed. The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A)(1)

Complaint Item: 30 - No railing on front of house.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, the railing was missing at the front of the house as well as the missing stair case leading up to the second floor apartment. The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A)(1)

Complaint Item: 31 - Trench not backfilled.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, at the rear left corner of the property there was a utility trench opened and partially backfilled over time from weather. The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A)(1)

Complaint Item: 32 - Utilities exposed.

Investigator’s Observation: As indicated in Item 23.Verified. At the time of the Inspection it was observed, there were wire as well as conduit out of the ground where the pool equipment was once located and was never reinstalled during the reconstruction of the project. The utilities that were exposed did not appear to be safe. The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A)(1)

Complaint Item: 33 - Soffit and fascia not completed.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, the soffits and fascia on the front and the left side of the house where the apartment is located were not completed, the rough construction lumber is visible. The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A)(1)

Complaint Item: 34 - Lighting in garage broken.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, the light in the garage on the ceiling where the water leak happened from the upstairs apartment. The drywall was damaged and the light was removed. The light is now hanging by the wires and the power is still active in the garage. The Respondent will need to correct this by the appropriate means.

Governing Rule: Abandonment of a contract or refusal to perform after submitting a bid on work without legal excuse for the abandonment or refusal. A.R.S. § 32-1154(A)(1)

Complaint Item: 35 - Water heater platform, and drain incorrect. Investigator’s Observation: Verified. At the time of the Inspection it was observed the water heater was installed in a closet in the garage. In the closet there was a drain plumbed into the main house. The pan the water heater sits on also has a drain, the drains for both do not line up with each another. If water was to fill the pan for any reason the water would cause damage since it would not drain where it's intended. The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A)(3) - R4-9-108(A) Workmanship

Complaint Item: 36 - Internet cable across sidewalk.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, the fiber optic communication line was placed over the sidewalk causing a tripping hazard since there was no conduit ran to the house to keep this line underground until it needed to enter the house. The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A)(3) - R4-9-108(A) Workmanship

Complaint Item: 37 - Hole in guest room wall.

Investigator’s Observation: Verified. At the time of the Inspection it was observed, there was a hole in the wall right above the baseboard. The Respondent will need to correct this by the appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A)(3) - R4-9-108(A) Workmanship

Complaint Item: 38 - No pantry door.

Investigator’s Observation: Verified. At the time of the Inspection it was demonstrated, the pantry door did not exist, the jamb and trim were the only thing in place. The jamb did not have hinge placement or a place for a door to latch. The Respondent will need to correct this by the app appropriate means.

Governing Rule: Violation of any rule adopted by the Registrar; Namely A.A.C. R4-9-108(a): A contractor shall perform all work in a professional and workmanlike manner. A.R.S. § 32-1154(A)(3) - R4-9-108 Workmanship. (A)

ITEMS NOT REQUIRING CORRECTION

The following complaint items require no action by the Respondent:

Complaint Item: 1 - Abandonment. Don took a full-time job 61 of 2024 abandoning my project with no notice to me

Investigator’s Observation: This is a general statement and does not implicate a specific workmanship issue. It therefore cannot be evaluated by the ROC.

Governing Rule: Not Applicable

Complaint Item: 2 - Did not complete the job I specific date on 531/2024. resulting in nearly $20,000 of rent.

Investigator’s Observation: This is a general statement and does not implicate a specific workmanship issue. It therefore cannot be evaluated by the ROC.

Governing Rule: Not Applicable

Complaint Item: 3 - Overcharged four and did not complete concrete, site prep, nor framing.

Investigator’s Observation: This complaint item alleges a financial dispute with a licensed contractor, it alleges nothing indicating grounds for discipline. The ROC has no jurisdiction over this matter.

Governing Rule: Not Applicable

Complaint Item: 4 - Overcharged for sales tax.

Investigator’s Observation: This complaint item alleges a financial dispute with a licensed contractor, it alleges nothing indicating grounds for discipline. The ROC has no jurisdiction over this matter.

Governing Rule: Not Applicable

Complaint Item: 7 - Overcharged for General conditions. I paid him $25,000.

Investigator’s Observation: This complaint item alleges a financial dispute with a licensed contractor, it alleges nothing indicating grounds for discipline. The ROC has no jurisdiction over this matter.

Governing Rule: Not Applicable

Complaint Item: 13 - He raised the house above and beyond what was wanted or required.

Investigator’s Observation: This is a general statement and a broad allegation and does not implicate a specific workmanship issue. It therefore cannot be evaluated by the ROC. At the time of the inspection the complainant could not demonstrate this allegation.

Governing Rule: Not Applicable

Complaint Item: 14 - He kept changing the scope of the work on pay requests.

Investigator’s Observation: The ROC has no penalties for poor attendance, lack of communication, or poor customer service.

Governing Rule: Not Applicable

Complaint Item: 16 - Several electrical outlets were in wrong location and had to be relocated.

Investigator’s Observation: Unable to verify, no evidence to prove or disprove complaint item constitutes poor work due to the complaint item being modified and/or corrected by another contractor prior to the inspection, ARS §32-1155 (D)(2)

Governing Rule: Not Applicable

Complaint Item: 20 - Electrical to HVAC had to be redone.

Investigator’s Observation: Unable to verify, no evidence to prove or disprove complaint item constitutes poor work due to the complaint item being modified and/or corrected by another contractor prior to the inspection, ARS §32-1155 (D)(2)

Governing Rule: Not Applicable

Complaint Item: 21 - Wrong toilets were ordered and installed and had to be replaced.

Investigator’s Observation: Unable to verify, no evidence to prove or disprove complaint item constitutes poor work due to the complaint item being modified and/or corrected by another contractor prior to the inspection, ARS §32-1155 (D)(2)

Governing Rule: Not Applicable

8. Complainant failed to comply with the Directive.

9. On May 8, 2025, the Registrar issued a Citation against Respondent’s license alleging that Respondent had violated Ariz. Rev. Stat. § 32-1154(A)(1), Ariz. Rev. Stat. § 32-1154(A)(2)(a), Ariz. Rev. Stat. § 32-1154(A)(3) - R4-9-108(A), Ariz. Rev. Stat. § 32-1154, (A) (8), Ariz. Rev. Stat. § 32-1154(A) (12) - Ariz. Rev. Stat. § 32-1158, and Ariz. Rev. Stat. § 32-1154(A) (22).

10. Respondent filed a timely answer to the Citation.

11. The matter was referred to the Office of Administrative Hearings for an evidentiary hearing.

12. At hearing, Investigator Otero testified consistently with his job-site inspection notes and the Directive. Ms. Bock agreed with the findings of Investigator Otero.

13. Mr. Williamson disputed Investigator Otero’s findings regarding Complaint Items 12, 22, 32, 36, and 38. Mr. Williamson disputed Complaint item 12 because demolition was excluded from the contract. Mr. Williamson disputed Complaint Item 22 because Complainant did not provide Respondent with a plan for rain water drainage.

The Administrative Law Judge finds that demolition was specifically excluded from the contract. The contract also provides that Complainant was responsible for furnishing all EPA Ground/Storm water permits and plans. Accordingly, the Administrative Law Judge finds that Respondent was not required to demolish the existing concrete or install gutters because Complainant did not provide Respondent with the required plans.

14. Regarding Complaint Item 32, Mr. Williamson stated that the conduit was abandoned, and therefore, any work would have been excluded demolition work.

The Administrative Law Judge finds that the contract included electrical work and there was no evidence that the conduit was excluded. The Administrative Law Judge finds that Respondent provided insufficient evidence to establish that the conduit was excluded from the contract or was otherwise abandoned by Complainant.

15. Regarding Complaint Item 36, Mr. Williamson stated that internet cable was not included in the contract and that the utility company installed the cable.

The Administrative Law Judge finds that there is insufficient evidence to establish that Respondent caused the trip hazard or was otherwise required to install the fiber optic cable.

16. Regarding Complaint Item 38, Mr. Williamson stated that the pantry door was left at the job-site. The Administrative Law Judge finds that there is insufficient evidence to establish that Respondent failed to deliver the pantry door to the jobsite or removed the door from the jobsite. Nonetheless, it is undisputed that the Respondent did not install the pantry door.

17. Respondent did not dispute the findings of Investigator Otero regarding any other Complaint Items listed in the Directive.

18. Administrative notice is taken of the Registrar’s public website. According to the information available on the website on September 23, 2025, Respondent’s license was first issued on September 28, 2022, and is inactive. Such prior License record also shows that there is only one open complaint against Respondent. Respondent’s license has never been disciplined. The lack of prior discipline taken is considered a mitigating factor in the imposition of discipline and a civil penalty.

CONCLUSIONS OF LAW

This matter lies within the Registrar’s jurisdiction. See Ariz. Rev. Stat.

§ 32-1101 et seq.

Complainant bears the burden of proof to establish Respondent’s statutory violation by a preponderance of the evidence. See Ariz. Rev. Stat. § 41-1092.07(G) (2); Arizona Administrative Code (hereinafter “A.A.C.”) R2-19-119(A) and A.A.C. R2-19-119(B) (1); see also Vazanno v. Superior Court, 74 Ariz. 369, 372, 249 P.2d 837 (1952). “A preponderance of the evidence is such proof as convinces the trier of fact that the c52ontention is more probably true than not.” Morris K. Udall, Arizona Law of Evidence § 5 (1960).

The preponderance of the evidence shows that Respondent abandoned the

project regarding the Complaint Items listed in the Directive, except Complaint Items 12 and 22, in violation of See Ariz. Rev. Stat. § 32-1154(A) (1).

The preponderance of the evidence shows that Respondent did not perform

the work in a professional and workmanlike manner regarding the Complaint Items listed in the Directive, except for Complaint Item 36, which is a violation of A.A.C. R4-9-108(A), and thereby of See Ariz. Rev. Stat. § 32-1154(A)(3).

5. The preponderance of the evidence shows that Respondent did not

obtain a permit for the project through the city of Paige, which is a violation of Ariz. Rev. Stat. § 32-1154(A) (2) (b).

6. The preponderance of the evidence shows that Respondent failed in a

material aspect to complete construction for the price stated in the contract, which is a violation of Ariz. Rev. Stat. § 32-1154(A) (8).

7. The undisputed evidence established that Respondent’s contract did not include a statement that the property owner has the right to file a written complaint with the Registrar for alleged violations of Ariz. Rev. Stat. § 32-1154(A), which is a violation of Ariz. Rev. Stat. § 32-1154(A) (12) and Ariz. Rev. Stat. § 32-1158.

8. The preponderance of the evidence shows that Respondent failed to comply with the Registrar’s Directive regarding without valid justification, which is a violation of Ariz. Rev. Stat. § 32-1154(A) (22).

RECOMMENDED ORDER

Based on the foregoing, it is recommended that on the effective date of the Order, the Registrar shall suspend License No. 340994 issued to Mariner LLC, for three days. It is further recommended that the Registrar require Respondent to pay the sum of $500.00 as a civil penalty pursuant to Ariz. Rev. Stat. section 32-1154(E).

It is further recommended that if Respondent fails to pay the entire amount of the civil penalty on or before thirty days following the effective date of the Registrar’s final order, the Registrar revoke Respondent’s license, effective on such deadline date.

No future license shall be issued to any entity consisting of persons associated with Respondent, as defined in Ariz. Rev. Stat. section 32-1101(A) (7), unless Respondent tenders payment of any outstanding prior civil penalty.

It is further recommended that within thirty days of the effective date of the final order, Respondent shall provide to the Registrar copies of its form contract that has been revised to comply with the requirements of Ariz. Rev. Stat. § 32-1158(A). If Respondent fails to provide proof that it has so revised its form contracts, it is recommended that Respondent’s license be suspended for three days.

Pursuant to A.R.S. § 41-1092.08(I), the licensee may accept the Administrative Law Judge Decision by advising the Office of Administrative Hearings in writing not more than ten (10) days after receiving the decision. If the licensee accepts the Administrative Law Judge Decision, the decision shall be certified as the final decision by the Office of Administrative Hearings.

In the event of certification of the Administrative Law Judge Decision by the Director of the Office of Administrative Hearings, the effective date of the Order will be forty (40) days from the date of that certification.

Done this day, September 23, 2025.

/s/ Velva Moses-Thompson

Administrative Law Judge

Transmitted by either mail, e-mail, or facsimile to:

Tom Cole, Director

Registrar of Contractors

Wendy Bock

[email redacted]

Claudio E. Iannitelli, Esq.

IANNITELLI MARCOLINI P.C.

[email redacted]

Mariner LLC

[email redacted]

By: OAH Staff