STATE OF ARIZONA IN THE OFFICE OF ADMINISTRATIVE HEARINGS
|MICHAEL AND PEGGY BENGSON, | |Case No. 03-0412 | | | |Docket No. 03F-0412-ROC | |Complainant, | | | | | | | |-v- | |DECISION OF ADMINISTRATIVE LAW JUDGE| | | | | |License No. 064831 , Class B-05 of | | | |Independent Concrete Inc. dba | | | |SUN POOLS (CORP), | | | | | | | |Respondent. | | | | | | |
HEARING: February 3, 2003 at 9:00 a.m.
APPEARANCES: The Complainants appeared in their own behalf. The Respondent failed to appear.
ADMINISTRATIVE LAW JUDGE: Robert I. Worth _____________________________________________________________________
Evidence and testimony were presented, and based upon the entire record, the following Findings of Fact, Conclusions of Law and Recommended Order are made.
FINDINGS OF FACT
1. The hearing in the above-entitled matter was scheduled on advance written notice duly sent to both parties. Although the start of the scheduled hearing was delayed for over twenty-five minutes to afford added time in which to make an appearance, the Respondent failed to appear either through any properly authorized corporate employee or through any legal representative.
2. Pursuant to a written proposal and contract, Respondent agreed to and did construct a pool and spa on Complainants’ property. The agreement incorporated
specific plans and drawings containing the shapes and dimensions for the pool and spa structures and also reflecting the inclusion of a fully described and detailed water feature that was a spillway connecting the spa to the pool. The stated original contract price was $48,197.69, all of which was fully paid by Complainant to Respondent.
3. Further additional billings were sent by Respondent and either paid or partially paid by Complainants. The first of such billings related to an asserted extra charge for a hard dig that never was the subject of a change order or of any prior advance notice to Complainant as to the need or the amount. Another added charge was subsequently billed for extra shotcrete resulting from an increase in the width of the pool exceeding the dimensions expressly specified in the applicable plans. No request for such added dimensions nor any advance notice to or authorization by the property owners was sought or given with respect to the increased width provided.
4. One of the above-described extra billings, relating to a claimed hard dig, was in the amount of $5,492.99, all of which was paid by Complainants who, although communicating an objection based upon the lack of any change order or of any other mutual agreement as to the need and the anticipated total amount, did not want to have any delays in completing the project.
5. The second extra billing, relating to a claim for extra shotcrete, was presented almost eight months after the normal shotcrete stage billing and was originally in the amount of $5,991.00. Once again, Complainants were desirous of having the construction proceed to the pebble- tec stage, and a reduction in the amount billed was agreed upon decreasing the billing to $2,610.00, representing a revised rate of $87.00 per yard for the reported use of an extra 30 cubic yards of shotcrete. Complainants were shown to have paid one-half of such adjusted billing, or $1,305.00, to Respondent.
6. The payment by Complainants of the $48,197.69 original contact amount plus the $6,797.99 combined amounts of the above-described additional payments to Respondent resulted in an aggregate of total payments made by Complainants to Respondent in the sum of $54,995.68.
7. A portion of the contemplated pool and spa construction work was to and did include a water feature that would form a spillway designed to carry water from the spa to the pool. The construction by Respondent of this water feature or spillway was to consist of boulders set in shotcrete and was shown by the Complainants’ uncontroverted testimonial and documentary evidence to materially and prejudicially deviate from the applicable plans and specifications, especially with respect to the quantity, size and positioning of the installed boulders or rocks that were to eliminate or reduce the visibility of the underlying shotcrete.
8. Credible evidence tended to demonstrate that a water leak had developed and continues to be experienced from the shotcrete edge of the water feature or spillway. Although notified of such deficiency, Respondent has never repaired the leaking condition that still exists. In point of fact, Respondent was shown to have refused to rectify any reported problems until or unless the remaining unpaid balance claimed for one of the extra charge billings was transmitted. In this case, the ongoing water leakage was further shown to tend to create a realistic danger of adversely affecting the entire waterway structure as well as the adjacent landscaping.
9. Any such asserted claim of non-payment, even if valid, would not operate as a defense to a licensee with respect to the contractor’s applicable obligation to rectify workmanship deficiencies, since adequate remedies at law would be available for the collection of unpaid and owing monies. Respondent’s failure and refusal to timely respond to and to remedy the reported leaking condition, thereby tending to adversely impact upon the underlying and adjacent surface and subsurface, is further determined
also to constitute a wrongful act to the detriment of Complainants and their property within the meaning of one of the statutory subsections charged herein to have been violated by Respondent.
10. Following a jobsite visit, the Registrar’s assigned Inspector issued a written Corrective Work Order to Respondent after having confirmed the water feature’s deviation from plans and the need for remedial work to eliminate the water leak.
11. The Inspector’s analysis and evaluation also incorporated an appropriate determination placing responsibility for hard dig expenses and for extra shotcrete costs upon the Respondent. These expenses were deemed attributable to the fact that Respondent had exceeded the width dimensions for the pool that were specified on the applicable plans. Because of the topography of Complainants’ lot, most all of the pool structure had been designed to be located in an area that was to be predominantly over filled and compacted dirt. Respondent’s erroneous enlargement of the excavated width of the pool, beyond the specified dimensions, was the proximate cause of the need for a hard dig in a location never intended to be part of the installed pool. Similarly, the enlargement as to width, never previously requested or authorized by Complainant, was the primary reason that added shotcrete materials would be and were needed.
12. Having determined that the purported charges for a hard dig and for additional shotcrete materials were improper and unwarranted in this case, the Inspector’s directive to Respondent included a duty to take appropriate action with respect to the added billings in addition to accomplishing needed corrections of the water feature’s deviations and its leaking condition. The undisputed evidence revealed that Respondent has not complied with the terms of the Inspector’s directive.
13. It is found and determined that the imposition by Respondent of hard dig charges was inappropriate under all the circumstances. No necessity for any hard dig
in the area where the pool was designed to be constructed was shown have existed, and such added work would, therefore, be unnecessary, except potentially in the area where the pool dimensions were exceeded.
14. Similarly inappropriate would be the asserted and billed extra charges for added shotcrete that would be needed as a result of the erroneous over-digging by Respondent of the excavated pool without advance authority. There was there no advance mutual agreement to pay added amounts for extra shotcrete, and when Complainant had subsequently agreed to allow the larger pool dimensions to remain, no claim for extra costs was mentioned at the time nor for many months thereafter. Complainants would be entitled to be informed of the existence and amount of extra charges before deciding whether or not to require Respondent to adhere to the specified smaller pool dimensions.
15. Undisputed credible testimony, corroborated by the assigned Inspector, tended to indicate that correction of the waterway at this time could be properly achieved only by a complete removal and replacement of the entire feature and the use of more and/or larger boulders set in shotcrete. It was sufficiently and credibly demonstrated that the present minimum cost for such remedial measures would be a sum not less than $6,500.00.
16. The prolonged duration of unresponsiveness by Respondent, especially with respect to rectifying the reported leaking condition, as well as to the required correction of the demonstrated deviations from plans of the constructed waterway, serves to justify not affording belated opportunities to remedy these valid complaints at this time. These failures, coupled with the attempt to impose added charges relating to a mistake in measurements of width dimensions on the part of or otherwise attributable to Respondent, serve to support a finding that Respondent has not completed the construction project for the agreed contractual price. Such ongoing conduct and
inaction on the part of Respondent is further found to reflect a disregard of its duties as a licensed contractor in this State as well as of the entitlements and comforts of its customer, the Complainants. In this case, the use by the Registrar of the discretionary statutory authority to formulate a condition based upon the making of restitution to Complainants for the minimum projected remedial cost of $6,500.00 is justified and fully warranted.
17. The evidence also supports the inclusion in the Registrar’s Order of a further condition consisting of the return by Respondent of all monies paid by Complainants for purportedly extra work relating to a hard dig and to additional shotcrete, both of which were made necessary only because of Respondent’s own mistakes in measurement. Such further restitutionary payments should be in the respective amounts of $5,492.99 and $1,305.00, or a combined total amount of $6,797.99.
18. By the failure of Respondent to appear at and participate in the scheduled hearing of this matter, no evidence in defense or in mitigation of the charged violations was presented to the tribunal.
19. Notice is taken of the Registrar’s license records, which reveal that Respondent has compiled a highly satisfactory prior record as a contractor. This good prior record should prompt the Registrar of Contractors not to impose any additional or lingering penalties against Respondent in this case other than a provisional license suspension conditioned upon the filing of proof that Respondent has complied with the payment terms of this Order.
CONCLUSIONS OF LAW
1. The undisputed evidence of record adequately established that, as charged in the issued Citation, Respondent has violated the provisions of A.R.S.§32-1154(A)(2), (7), (9), (23) and (3); namely, Rule R4-9-108, A.A.C.
2. Although it is not a proper function of either the Office of Administrative Hearings or the Registrar of Contractors to adjudicate and award money damages which must be recovered, if at all, through pursuit of a civil court action, the Registrar is empowered by statute to impose reasonable conditions which may serve to reduce or eliminate any otherwise appropriate disciplinary penalties for proven violations of the State’s contracting laws. Whenever the contractor’s performance of corrective or remedial measures on a jobsite is no longer warranted, the inclusion of a condition in the nature of restitution, total or partial, is fully appropriate and equitably justified. Such authorization to provide for restitution from a contractor to a prevailing party in an administrative action has been legally upheld in Sunpower of Arizona v. Arizona State Registrar of Contractors, 166 Ariz. 437, 803 P.2d 430 (1990), and subsequently was expressly confirmed by the statutory enactment of A.R.S.§32-1156.01. In this way, a Complainant in an administrative action who has sustained the burden of proving contracting law violations does not have to await the outcome of protracted civil litigation in order to recover at least a portion of a demonstrated loss and, of equal or perhaps greater significance, a licensed contractor/Respondent is given the means to control, to some extent, the severity of any disciplinary penalty. Moreover, any amounts paid in satisfaction of a condition affecting licensure may properly be evaluated, credited or applied against any civil judgment ultimately obtained in favor of either party.
3. The evidence adduced at the hearing adequately supports the inclusion in the Registrar’s Order of a condition consisting of the payment or tender by Respondent to Complainants of the total sum of $13,297.99, representing restitution for the minimum anticipated expenses to correct the plan deviations and leaking condition of the water feature plus the return of all sums previously paid by Complainants against inappropriate billings for hard dig and extra materials expenses. ……. ……. …….
RECOMMENDED ORDER
In view of the foregoing, it is recommended commencing on the effective date of the Registrar’s Order that the Class B-05 license of Respondent be suspended until the Registrar receives proof that Respondent has paid or tended to Complainants the amount of $13,297.99.
It is further recommend that if proof of Respondent’s payment of the above-provided monetary sum is filed with the Registrar on or before this Order’s effective date, then no license suspension shall be imposed and the entire Citation and Complaint in Case Number 03-0412 shall be closed.
Dated: February 12, 2003. OFFICE OF ADMINISTRATIVE HEARINGS
______________________________________ Robert I. Worth Administrative Law Judge
Original transmitted on _____________________
by: _____________________________ , to:
Michael P. Goldwater, Director Registrar of Contractors 800 West Washington Street (6th Floor) Phoenix, AZ 85007
ATTN: Jennifer Brown
-----------------------
Office of Administrative Hearings 1400 West Washington, Suite 101 Phoenix, Arizona 85007 (602) 542-9826