03F-0359-ROC · Registrar of Contractors · 2003-01-30

IN THE OFFICE OF ADMINISTRATIVE HEARINGS

|LEILLA AND RON | | No. 03F-0359-ROC | |KRAMER, | |ADMINISTRATIVE | | | |LAW JUDGE DECISION | |Complainants, | | | | | | | |-v- | | | | | | | |LICENSE NO. 147599, CLASS KB-02 | | | |ROADRUNNER CONSTRUCTION TILEWORKS, | | | |INC. dba | | | |FORRER CONSTRUCTION (CORP), | | | | | | | |Respondent. | | | | | | |

HEARING: January 18, 2003. APPEARANCES: The Complainants appeared personally and were represented by their attorneys, Joel E. Sannes, Esq., and Kristine A. Kunkel, Esq. The Respondent was represented by its attorney, Douglas G. Wymore, Esq. ADMINISTRATIVE LAW JUDGE: Brian Brendan Tully _____________________________________________________________________ Evidence and testimony were presented and, based upon the entire record, the following Findings of Fact, Conclusions of Law and Recommended Order are made:

FINDINGS OF FACT

1. This matter came on for hearing on the charges made against Respondent in the Citation and Complaint issued by the Registrar of Contractors. The Citation alleges that Respondent possibly violated the provisions of Arizona Revised Statutes § 32-1154(A)(1), (2), (7), (23) and (3); namely Arizona Administrative Code Rule 4-9-108. The Citation was issued as a result of a complaint filed with the Registrar by Complainants against Respondent. 2. Respondent is the holder of License No. 147599, a Class KB-02 dual residential and small commercial contracting license, issued by the Registrar. 3. The Complainants moved to Arizona during the summer of 2002. 4. The Complainants purchased an existing residence located at 2133 W. Elliot Road, Chandler, Arizona. 5. After purchasing their residence, the Complainants decided to remodel their outdoor patio and pool areas with a landscaping project, which also included hardscaping. 6. On or about July 17, 2002, Respondent presented Complainants with a bid for their complete landscaping project. The scope of that bid included the following:

A) Redo front yard landscape. $500.00. B) Beehive fireplace with 9’ bench each side; buff colored stucco. $4,080.00. C) Barbeque (8’ long with electrical outlet in backsplash); Barbeque unit and door supplied by homeowners; includes a flagstone top on the barbeque cabinet. $1,980.00. D) Front and rear sod removal; also remove kool-deck pad and kool- deck step stones; prepare for granite placement. $1,000.00. E) Flagstone patio at existing patio, new decks, approximately 1,230 square feet area. F) Re-landscape rear yard: new drip system, spread rock, place stepping stones from pool to shower, garage back door pad, provide niche lighting for front and rear of property, and install a shower head at side of house.

7. On or about July 23, 2002, Respondent submitted an offer for the following scope of hardscaping work, which was accepted in writing by Complainants:

(B)$4,080.00, includes six niche lights stubbed to rear of fireplace. (C)$1,980.00 plus $500.00 for bar, includes 3 niche lights. (E)$10,800.00 for flagstone patios; $4,300.00 for extra flagstone at pool.

8. It is determined that Respondent’s use of the circled letters in the written agreement accepted by Complainants incorporated by reference the scope of work with correlating circled letters in its original bid, except where the written agreement further described additional items of work. 9. The Respondent gave Complainants a 10% discount. The total contract price, including tax in the amount of $1,462.00, totaled $20,956.00. 10. The parties’ agreement provided that Complainants would pay Respondent a down payment in the amount of $10,956.00. The Complainants did pay that amount to Respondent. 11. The parties’ agreement further provided that $5,000.00 would be paid to Respondent “as work progresses”. The balance of the contract price is due upon completion. 12. During construction Complainants paid Respondent the $5,000.00 progress payment when requested to do so by Respondent. 13. Respondent did not get the landscaping portion of the project. That scope of work was awarded to Jorge Noriega, who is an unlicensed contractor. Mr. Noriega testified that he is in the process of obtaining a contracting license. 14. Mr. Noriega was originally asked to build the beehive fireplace by the Complainants but he declined to do so because he was not licensed. 15. Complainants asked Mr. Noriega to be in charge of the total landscape and hardscape project. They specifically authorized him to supervise Respondent’s work in their absence, which he did do. Such contracting activity by Mr. Noriega required him to possess the appropriate contracting license, which he did not, and does not, have. Therefore, the Complainants’ criticism that Respondent failed to properly take directions from Mr. Noriega is not valid. Any argument that Mr. Noriega was merely Complainants’ agent does not overcome the requirement that such supervision be undertaken only by a licensed contractor. 16. The Complainants selected the design of the beehive fireplace with winged bench seating from a photograph catalog of prior fireplaces constructed by Respondent. There were no plans or drawings prepared by Respondent or requested by Complainants. 17. Prior to the construction of the fireplace and bench seating, Complainant Ron Kramer and Respondent’s president and qualifying party, Tony Forrer, discussed the placement and setting for the unit. 18. Complainants are found to have approved the location of the fireplace and bench seating which they now complain about. Mr. Kramer was present with Mr. Forrer when the latter laid out the outline of the fireplace and bench seating with spray paint for the concrete. Mr. Kramer is found to have approved the painted outline. Mr. Kramer was also present when the outline for the fireplace and bench seating was outlined with keel on the poured slab. Mr. Kramer is also found to have approved that outline. 19. After the fireplace and seating were constructed, but prior to final completion, Complainants complained to Respondent that the fireplace and seating were not constructed as instructed by the Complainants. The Complainants wanted the fireplace and seating turned more towards the north wall so that the fireplace could be viewed from across the swimming pool from the patio located due east of the fireplace. As constructed, the fireplace is less visible from the patio, but is visible from the swimming pool and the barbeque, which is located southeast of the fireplace and south of the patio. 20. The dispute about the location of the fireplace escalated between the parties. Complainants insisted that Respondent remove and replace the structure at its sole cost and expense. Respondent contended that Complainants had twice approved the location of the structure and refused to incur the expense to remove and replace it. 21. On or about August 16, 2002, things came to a head when Mr. Forrer met with Mr. Kramer at the jobsite. Mr. Forrer then ordered Respondent’s workers off the jobsite. At that time there were flagstone pieces laid throughout the backyard that had not been set. There was also construction debris present. 22. On or about August 19, 2002, Mr. Forrer again met with Mr. Kramer to discuss the dispute. There is no credible evidence that Mr. Forrer admitted to Mr. Kramer that Respondent made a mistake as to the location. 23. On or about August 19, 2002, Respondent sent Complainants a written addendum and a written revision of the contract for their approval and signatures. Each document contained the following handwritten language above the location for Complainants’ signature line for indicating acceptance: “Your signature is an identifying mark that Roadrunner will get paid for all work performed.” 24. The addendum covered the following described work performed and completed by Respondent at Complainants’ request but without prior agreement as to pricing:

A. Patio at front entry approx. 280 sq. ft./ concrete base/saltillo tile application. $1,780.00. B. Flagstone bench at barbeque. $520.00. C. 2.5 to 3’ additional barbeque length. $530.00

The pricing submitted to the Complainants by Respondent had not been previously negotiated and accepted. In the addendum Respondent agreed to subtract a $500.00 discount from that total. Respondent also agreed to paint areas of the stucco wall damaged by Respondent. 25. The revision submitted by Respondent included three barbeque doors for $364.00. It showed an outstanding balance of $5,000.00. 26. The Complainants refused to sign the addendum and revision. 27. On or about August 20, 2002, Complainants filed a complaint against Respondent with the Registrar of Contractors. The Complainants later also filed a civil lawsuit against Respondent. That lawsuit is still pending. 28. In response to the Complainants’ complaint, the Registrar’s assigned agency inspector, Mel Purchase, performed a jobsite inspection on September 10, 2002. The inspector viewed the laid out flagstone pieces, a pile of sand located in Complainants’ driveway, the beehive fireplace with winged seating and the barbeque. 29. Inspector Purchase opined that construction of the barbeque seemed complete. 30. After completing his inspection, Inspector Purchase issued a Corrective Work Order dated September 12, 2002 directing Respondent to timely perform remedial work to the following areas of deficient workmanship within 15 days from the date of the written directive:

a) Respondent was directed to correct the chip damage to the newly built wall. b) Respondent was to complete the flagstone decking. c) Respondent was required to obtain a building permit and have all inspections done as required by the local municipality.

31. The Corrective Work Order did not require Respondent to perform any remedial work to the fireplace and seating areas. Inspector Purchase testified that he could not determine if the location was incorrect. He further noted that Complainants do not have any workmanship issues with those areas, just their location. 32. Respondent filed a preliminary lien notice against the Complainants’ property. 33. On or about September 23, 2002, Mr. Kramer had a telephone conversation with Doris Fields, the office manager of Prelien Services, asking questions about the preliminary lien process. It is determined that during that conversation Mr. Kramer made the following statement referring to Mr. Forrer: “If he finds himself floating in the river, I guess that will take care of the problem.” Mr. Forrer became aware of the conversation that Mr. Kramer had with Ms. Fields. 34. There is credible evidence that Mr. Kramer and another individual, both wearing fatigues and driving Mr. Kramer’s Hummer, went to Mr. Forrer’s former residence looking for him. It is determined that Mr. Kramer aggressively badgered the new homeowners for Mr. Forrer’s present address. (Mr. Kramer is a weight lifter who appears to be well conditioned). The new owners did not give Mr. Kramer the requested information, but did relate the incident to Mr. Forrer. 35. Mr. Forrer made a complaint to the local police department concerning the aggressive statements and actions by Mr. Kramer described above. There is no indication that any criminal proceedings have resulted from the complaint. 36. Mr. Kramer had several telephone conversations with Inspector Purchase prior to the deadline to comply with the written directive. During a portion of his conversations Mr. Kramer stated to the inspector words to the effect that Mr. Forrer’s demise might not be a bad thing, and expressed other threats of legal and/or illegal forms of retribution against Mr. Forrer. 37. Prior to the September 27, 2002 deadline for compliance with the Corrective Work Order, Mr. Forrer expressed to Inspector Purchase concern for his personal safety based upon the threats and aggressive actions taken by Mr. Kramer. 38. On September 24, 2002 Mr. Kramer had a telephone conversation with Inspector Purchase. Mr. Kramer followed up on that conversation by letter of the same date sent to Mr. Purchase. In that letter Mr. Kramer wrote the following, among other things: “The fact that Mr. Forrer feels threatened is absolutely absurd. I don’t see how my comments made in frustration to an unrelated person can be taken as a threat. That is the same as if you are watching a football game and yelling ‘kill him’ at the screen.” 39. Inspector Purchase opined that Mr. Kramer had made threats against Mr. Forrer. 40. It is determined that Mr. Kramer has made credible threats against Mr. Forrer, who is justified in his concern for his personal safety. 41. Respondent did not comply with the Registrar’s written directive by September 27, 2002. However, it is determined that Mr. Kramer’s repeated threats against Mr. Forrer were valid justifications for his non- compliance with that order. 42. By letter dated September 30, 2002, Mr. Kramer wrote another letter to Inspector Purchase and requested that his complaint be amended to include three additional items: cracks in the Complainants’ driveway allegedly caused by Respondent’s employees; a pile of sand left in the driveway by Respondent; and cracking in the exterior saltillo tile at the front entry to the house. 43. Inspector Purchase performed a second jobsite inspection to view the addendum workmanship. That inspection resulted in the issuance of a second Corrective Work Order dated October 10, 2002, which required Respondent to perform the following corrective work:

a) There is a large pile of sand in the Complainants’ driveway. The sand is intended to be used in the installation of the flagstone in the backyard. The Respondent was required to correct by appropriate means. b) There are two cracks in the grout joints in the saltillo tile entryway. Respondent was required to correct by appropriate means.

44. Inspector Purchase did not require that Respondent perform any repairs to the driveway. He did find cracking and tire marks, but he could not determine how or when the cracks occurred. 45. Respondent did not comply with the second Corrective Work Order because of Mr. Kramer’s threats. It is determined that Mr. Kramer’s threats were credible threats to Mr. Forrer’s safety and potentially also to Respondent’s workers. Therefore, Mr. Forrer was justified in not complying with the written directive. 46. Notwithstanding the two findings that Respondent was justified in not performing remedial repairs due to the credible threats against him made by Mr. Kramer, Respondent is found not to have been justified in pulling his work crews from the jobsite and not performing any further work prior to the start of Mr. Kramer’s threats. Although the parties had a dispute as to the location of the beehive fireplace, there was absolutely no reason that Respondent could not have completed the installation of the flagstone deck in the backyard. Instead of completing the installation, Respondent left the loose flagstone lying unsecured on the ground making it virtually impossible for the Complainants to utilize their backyard. They had to move flagstone pieces to make small paths in their background.

The Barbeque

47. It is determined that the barbeque was contracted to be 8’ in length. By using the circled “C” in the accepted contract, it is found that it referenced circled “C” of the bid, which specified the 8’ length. The contract accepted by Complainants further expanded the scope of the barbeque with the notation “plus $500 for bar”. The barbeque was built to feet in length at the request of the Complainants. Respondent did not draft a written change order with pricing and require the Complainants to sign it before building the barbeque. Respondent later invoiced the Complainants for the added work. Respondent is found to be entitled to the reasonable added cost to build the 3 foot addition to the barbeque. This administrative disciplinary proceeding is deemed not to be the appropriate forum for resolving that issue. 48. There are no complaints concerning Respondent’s workmanship as to the barbeque. 49. Respondent did not commit a wrongful act by subsequently submitting an invoice for the additional three feet of barbeque to Complainants. That monetary dispute should more properly be resolved in the parties’ civil litigation.

The Beehive Fireplace and Wing Seating Areas

50. It is determined that Respondent constructed the beehive fireplace and winged seating areas as approved by Mr. Kramer. The Complainants’ videotape admitted into evidence shows an attractive unit. As Inspector Purchase testified, the fireplace and winged seating areas are located within four surrounding palm trees. 51. The weight of credible evidence supports a finding that Respondent constructed the fireplace and winged seating areas to minimum workmanship standards. 52. Thomas Wilcoxson, an estimator for Blooming Desert Landscaping, testified that the opening of the fireplace was not functional because he felt it was too small. Mr. Wilcoxson’s criticism is the first one concerning any problem with the opening of the fireplace. That issue is deemed to be outside the scope of this hearing. 53. Respondent did not commit a wrongful act by insisting on a change order to remove and construct a new fireplace and seating areas.

The Newly Built Block Wall

54. Respondent is found to be responsible for damages to the newly constructed block wall.

The Flagstone Decking and Pile of Sand

55. Respondent is found to be responsible for completing the flagstone deck installation utilizing the sand located in the Complainants’ driveway. 56. Because Respondent left the jobsite without justification prior to Mr. Kramer’s threats, some of the flagstone has broken. Respondent is deemed responsible for the replacement of damaged flagstone at its sole cost and expense. 57. There is an unresolved dispute as to the square footage of the flagstone decking to be installed. Mr. Forrer claims that the square footage is approximately 1,230 feet. Mr. Wilcoxson states that the square footage is 1,902 feet. It is unclear as to who has miscalculated the square footage.

Building Permit

58. The Respondent is responsible for obtaining a required building permit and for arranging all required inspections as directed by the Registrar of Contractors’ September 12, 2002 written directive.

Cracks in the Driveway

59. There is found to be insufficient evidence to support a finding that Respondent caused the cracking in Complainants’ driveway. Their driveway is an older driveway. While the Respondent did utilize the driveway during the project, Complainants and the previous owners of their house also used the driveway.

Saltillo Tile

60. Respondent is responsible for repairing the two cracks in the saltillo tile at the entry to Complainants’ home. 61. The Complainants have not paid Respondent any amount for the saltillo tile installation. Respondent’s invoice for that work is not deemed a wrongful act. The parties never reached an agreement for the compensation to be paid to Respondent for that installation. The value of that work should be decided in their civil litigation. . . . 62. Inspector Purchase opined that Respondent did not abandon this jobsite. This tribunal agrees. While it was wrong for Respondent to remove its workers from the jobsite because of a dispute over the location of the beehive fireplace when there was still the extensive installation of the flagstone deck remaining to be performed, Mr. Kramer’s subsequent threats and actions toward Mr. Forrer justifiably gave the latter legitimate concerns for his personal safety and the safety of his workers. 63. The evidence of record supports a finding that Respondent did not deviate from plans or specifications on this project. 64. It is determined that Respondent failed to comply with local building code requirements by not obtaining a building permit and scheduling inspections as noted by Inspector Purchase in the first Corrective Work Order. 65. Respondent’s failure to obtain the required building permit, its action of removing its workers from the jobsite on August 15, 2002 when there was still flagstone decking work to be performed, and its failure to complete that installation prior to Mr. Kramer’s inexcusable threats concerning Mr. Forrer and his intimidation of third parties are deemed to be wrongful acts which have substantially injured the Complainants. 66. Respondent should be required to repair and complete the flagstone deck installation. However, it should do so without any intimidation from Mr. Kramer. A condition to Respondent’s completion of the flagstone deck installation should be that Mr. Kramer vacates his residence while Mr. Forrer or any of Respondent’s employees are performing work at the residence[1]. Respondent’s employees are not required to take any direction from Mr. Noriega unless he has become properly licensed. 67. It should be noted that there is no evidence that Mrs. Kramer acted inappropriately towards Mr. Forrer or any of Respondent’s employees during this project. 68. The Registrar of Contractors has a standing motion before the Office of Administrative Hearings that the Administrative Law Judge may review the official public records of any licensee found to have violated the provisions of the state’s contracting laws. A review of Respondent’s record reflects that this complaint is the only one of record with the Registrar.

CONCLUSIONS OF LAW

1. The Registrar of Contractors has jurisdiction over the Respondent and the subject matter in this case. 2. Pursuant to A.A.C. R2-19-119(B), the Complainants have the burden of proof in this matter. The standard of proof is a preponderance of the evidence. 3. The evidence of record is adequate to establish that Respondent violated the provisions of A.R.S. § 32-1154(A)(2), (7) and (3); namely A.A.C. R4-9- 108. 4. The evidence of record is insufficient to establish that Respondent violated the provisions of A.R.S. § 32-1154(A)(1) and (23). 5. Pursuant to the provisions of A.R.S. § 32-1154(B), the Registrar may impose discipline upon a licensee determined to have violated the provisions of the state’s contracting laws. A reasonable condition to be placed on Respondent’s license in order to avoid more severe disciplinary action is to require Respondent to complete the flagstone deck installation, subject to Mr. Kramer not being at home when such work is being performed by any of Respondent’s workers, including Mr. Forrer. If requested by the Complainants, Respondent should also be required to complete the fireplace and seating areas where presently located. 6. Based upon the totality of the evidence, the Administrative Law Judge declines to exercise his statutory authority, pursuant to A.R.S. § 32- 1156.01, to recommend that Respondent make any form of restitution to Complainants. It is concluded that the parties’ monetary disputes should properly be resolved in their civil action pending before the Superior Court of Maricopa County.

RECOMMENDED ORDER

In view of the foregoing, it is recommended commencing on the effective date of the entered Order in this matter that Respondent’s KB-02 license be suspended until the Registrar of Contractors receives written proof that Respondent has complied with the following conditions:

a) Respondent shall obtain the required building permit and shall schedule all necessary inspections. b) Respondent shall complete the installation of the flagstone deck. Respondent shall be responsible, at its sole cost and expense, for replacing damages flagstone. c) Respondent shall repair the cracks in the saltillo tile front entry by appropriate means. d) Respondent shall repair and repaint the damage to the block walls caused by its workers. e) Respondent shall remove all construction debris within its scope of work. f) If requested to do so by Complainants no later than ten days prior to the effective date of the Order entered in this matter, Respondent shall finish the beehive fireplace and adjoining seating areas where they are presently located. g) The requirement for Respondent to perform the above- described work is subject to the condition that Mr. Kramer not be at his residence while any of Respondent’s workers are performing any of the required work and that Mr. Kramer not have contact of any kind with Respondent’s workers while performing the required work, i.e. no telephone calls to the workers. h) Respondent’s workers shall not be required to take directions from Mr. Noriega, unless he has become properly licensed.

It is further recommended that if Respondent properly accomplishes the aforementioned corrective work on or before the effective date of the entered Order in this matter or if Complainants’ actions are contrary to the conditions set forth above, then the above-provided license suspension shall not take place. It is further recommended, in addition to the foregoing license suspension, if any, that Respondent’s KB-02 license be placed on active suspension for a period of five (5) days followed immediately by a period days probation. This additional disciplinary penalty shall commence on the effective date of the entered Order in this matter or the date on which notice of Respondent’s compliance with the terms of the entered Order is filed with the Registrar of Contractors, whichever is later.

Done this day, January 30, 2003

______________________________________ Brian Brendan Tully Administrative Law Judge

Original transmitted by mail this ____ day of ____________, 2003, to:

Michael P. Goldwater, Director Registrar of Contractors ATTN: Jennifer Brown 800 West Washington, 6th Floor Phoenix, AZ 85007

By ___________________________

----------------------- [1] Mr. Kramer, through counsel, offered to not be present during construction when Mr. Forrer would be present. See Exhibit 6. It is determined that the offer should also apply to when any of Respondent’s employees are working on the remainder of the project.

-----------------------

Office of Administrative Hearings 1400 West Washington, Suite 101 Phoenix, Arizona 85007 (602) 542-9826